News
Harpley Construction Update – February 2018
Our construction project teams have been back on site for over a month since the Christmas break and we are making good progress with construction underway in a number of precincts and on major infrastructure projects. Armstrong Road stage 1 is looking great and construction continues to extend this road through the Harpley project. Our first precinct in Larapinta, Stage 31, is due to title by April and we look forward to welcoming our first home builders on site in the coming months. The wetlands through Shearwater are progressing well and landscaping will commence soon. Read more for a construction update on all stages and projects currently underway:
.
Laparinta Stage 31
Status: Final civil works taking place including concreting and topsoiling of lots. Authority compliance testing has commenced.
Current Forecast Title Date: March-April 2018.
Shearwater Place Stages 51, 52, 53 & 54
Stages 51 & 54 Status: Sewer works complete. Stage drainage works underway with water main works to follow.
Current Forecast Title Date: June – July 2018.
Stages 52 & 53 Status: Sewer works to commence shortly.
Current Forecast Title Date: August – November 2018.
Wetlands Update
Shearwater Wetlands nearly ready for landscaping, Shearwater Place Wetlands well under way. Repairs and re-plantings to take place in Stage 4B wetlands, Carinya. Read more here.