Harpley Construction Update – August 2017
Harpley has been a hive of construction activity over recent months with the fairly dry weather allowing us to make good progress with construction of Shearwater stages 24 - 29, the adjoining wetlands, parts of Armstrong Road and Larapinta 31. Carinya Village Park is also well underway with expected completion in November.
Stage 24
Status: All main construction works complete, final authority approval being sought
Current Forecast Title Date: 31/08/2017
Stage 26
Status: Majority of main construction works complete, road asphalt works underway, line marking & street signs schedule for mid-August.
Current Forecast Title Date: 09/10/2017
Stage 29
Status: Services & road boxing complete, road subgrade currently being placed.
Current Forecast Title Date: 13/11/2017
Wetlands east of Shearwater
Drainage reserve complete, wetlands progressing well, started at northern section moving south.
Carinya Village Park
Status: Site grading and levels complete, footpaths also largely complete. Shelter structure has been erected. Click here to view a detailed plan of what the park will look like (artists impression only).
Due for completion: November 2017