Harpley Construction Update – March 2017


Harpley continues to grow with strong sales demand right through the summer months. From a construction perspective, we have had a couple of months of good weather and we are on track to deliver land titles as detailed below.

View our Construction Update Video

Carinya Stage 18

Construction works are complete, final authority approval currently being processed. Expected lodgement to titles office in the next week.
Settlement forecast early May 2017.

Shearwater Stage 21

Culverts works on Treeve Parkway are complete, all services placed, kerb & channel complete, as well as footpath works. Asphalt placement starts Monday 3rd April, with top soiling to lots & nature strips to follow.
Settlements are expected mid-June 2017.

Shearwater Stage 22

All services placed, kerb & channel complete, as well as footpath works. Asphalt placement starts Monday 3rd April, with top soiling to lots & nature strips to follow.
Settlements are expected mid-June 2017.

Shearwater Stage 24

Majority of services placed, partial kerb & channel complete, footpath works scheduled for early April.
Settlements expected early July 2017.

Shearwater Stages 25, 26, 28 and 29

Main sewer works complete for stages 25, 26 and 28. Services trenching & road box outs to commence shortly.

  • Stage 25 settlements expected early September 2017.
  • Stage 26 settlements expected early October 2017.
  • Stage 28 settlements expected early November 2017.

Shearwater Stage 29 sewer works expected to be complete by Friday 31st March, services trenching & road box out to follow.
  • Stage 29 settlements expected mid-November 2017.