Harpley Construction Update – November 2016 

Harpley continues to grow with strong sales demand right through Spring.  From a construction perspective, we are also growing very fast and despite the wet Spring weather, we are still on track to deliver land titles as scheduled.  There is lots of activity on-site this month with stages 14, 15, 16 and 17 just titled!

Stage titles are as follows:

View our Construction Update video

In our latest Construction Update video, we'll show you where the next stages of Shearwater are, plus the site of the future town centre and our next premium land release in Larapinta.

Carinya Titles Stages 14 to 17

Carinya Stage 14 construction was completed on the 3rd November 2016. Titles were received 1st December 2016. Carinya Stage 15 construction was completed on the 14th November 2016. Titles received 2nd December. Carinya Stage 16 construction was completed on the 18th November 2016. Titles received 2nd December. Carinya Stage 17 construction was completed on the 18th November 2016. Titles received 5th December 2016.

Carinya Stage 18

Road excavation has been completed, and kerb installed. Electrical & Communications infrastructure has been installed. Installation of potable & recycled water mains are now complete. Road subgrade & asphalt layers will commence in the coming weeks. Construction is forecast for completion mid-March 2017 with titles registration forecast for late April 2017.

Shearwater Stages 21 & 22

Sewer construction commenced early November 2016, Roads & Drainage and water services have recently commenced. The anticipated construction completion is mid-April 2017 with titles registration June 2017.