Living Here

Development Updates

 

Welcome to the June 2019 Development Update.

It's been an exciting month at Harpley with the commencement of piling for construction of the Ison Road Bridge occurring, and achieving approval for delivery of the balance of the Lendlease section of this road. The bridge over the future wetlands adjacent to the future Harpley town centre is a vital component of the road connection to enable us to complete the Armstrong/Ison Road section through Harpley by early 2020.

Harpley Town Centre has received subdivision approval from Wyndham City Council. The approval will allow the lots for the future town centre to be subdivided and sold to a development partner, with the first four lots on the market in June. Engineering designs will be submitted to council, with onsite civil works expected to commence before Christmas.

If you have any suggestions for improvements around Harpley send us a private message on Facebook.com/myharpley and we will see if we can assist.

Commencement of work on Ison Road Bridge

The Harpley development team is pleased to announce the commencement of piling for construction of the Ison Road bridge and achieving approval for delivery of the balance of the Lendlease section of this road. The bridge over the future wetlands adjacent to the future Harpley town centre is a vital component of the road connection to enable us to complete the Armstrong/Ison Road section through the Harpley project by early 2020. Click here to download a map showing the construction progress of Armstrong /Ison Roads and the location of the future Ison Road bridge.

Site Presentation

We have completed some turfing along Fairhall Avenue as an interim measure prior to these stages being constructed. Our contractors, YMCA continue to provide extra maintenance around the main streets of Harpley.

Also along Fairhall Avenue, we have completed the installation of 450m of vinyl hoarding skin which depicts images and messages about Harpley’s waterside lifestyle, future schools and future town centre. We hope you like the new hoardings which are designed to hide some of the construction works underway.

Shearwater Place Stage 52

We have now achieved titles on Stage 52 and settlements are occurring.

We welcome new residents to the Harpley community and wish you an exciting and quick build process.

Shearwater Place Stage 53

We are delighted to announce we have achieved titles on Stage 53. All purchasers are now in the process of being contacted and are preparing for settlement. Purchasers will have access to their lots soon and should check for survey pegs. For more information watch the video here.

We welcome new residents to the Harpley community and wish you an exciting and quick build process.

Townley Park Stages 62 & 63

Stage 62: We have now achieved titles on Stage 62. We welcome new residents to the Harpley Community and wish you a seamless build process.

Stage 63: We have now passed all authority audits. We are working with authorities for final sign offs and anticipate lodging for title registration no later than 25th June 2019.

Townley Park Stages 64 & 65

Stage 64: Electrical installation works are now underway and on schedule. As we approach completion of this stage we are now in a position to more accurately forecast titles. Title forecast for Stage 64 was previously advised as July - September 2019. We are now forecasting titles to August - September 2019.

Stage 65: Electrical installation works will follow on directly after Stage 64 electrical works are complete. We are now in a position to more accurately forecast title dates for this stage. We were previously forecast titles between July - September 2019. We are now forecasting titles in September 2019.

Townley Park Stages 66, 67 & 68

Stage 66: Bulk earthworks and sewer works are now complete. Detailed engineering approvals are still pending for this stage and approval is required prior to commencing road and drainage works. Approval is forecast for Jun-19. We are forecasting titles from Dec-19 to Feb-20.

Stage 67: Sewer and drainage works are now complete with water and road box out works underway. Titles are still forecast for Nov-19 - Jan-20.

Stage 68: Bulk earthworks for this stage are complete. Sewer works are scheduled to commence at the end of May 2019. There is no change to forecast titles with titles expected Feb-20 - Apr-20.

Wetlands Next to Shearwater Stages 28 & 29 and Shearwater Place Stages 51 & 54

The civil component of these wetlands is practically complete and planting works have commenced. Aquatics and specialist plants are scheduled for early spring to ensure the best chance for plant establishment. Residents can still expect an abundance of new landscaped areas to be opened throughout the 2019 calendar year.

Harpley Views Stage 81

Detailed engineering design approvals are pending for Stage 81. These plan approvals are required prior to commencement of detailed works on each stage. We are preparing for construction commencement and anticipate starting works over the coming month.

Titles were forecast for Nov-19-Dec-19. We are now forecasting titles between Feb-20-Apr-20. We apologise for the delays incurred.