Living Here

Development Updates

 

Information provided below is correct as at 26 November 2018.

Development to date

Construction at Harpley continues to progress well as we near the Christmas break and New Year shutdown, with the construction team due back on site on Monday 7th January 2019. The wetlands reserve and park adjoining stage 29 is progressing well and we hope to have this park open in time for Christmas. We have also commenced work on the wetlands reserve next to Larapinta Stage 33. Also to be completed before Christmas, we have made good progress on construction of Armstrong Road/Ison Road Stage 2A. This marks an important milestone as we work to complete this important road connection through the Harpley project.

In terms of stage construction, a number of stages across Larapinta, Shearwater Place and Townley Park are expected to title between December 2018 and April 2019. Townley Park stages 62-65 are expected to title in mid-2019, with Townley Park Stages 66-68 expected to title in the second half of 2019.

Larapinta Stage 33

All construction works have been completed, final authority approvals being sought.
Current Forecast Title Date: December 2018 – February 2019.

Shearwater Place Stage 52

All services & concrete kerbs have been installed, concrete footpaths & crossovers well underway with expected completion late November. Asphalt works to completed by early December.
Current Forecast Title Date: December 2018 - Feb 2019.

Shearwater Place Stage 53

Majority of services have been installed, concrete kerb has commenced and is due for completion early December. The road sub-base has been constructed with ashalt works due to commence shortly.
Current Forecast Title Date: Feb 2019 – April 2019.

Townley Park Stage 61

All construction works have been completed, final authority approvals being sought.
Current Forecast Title Date: December 2018.

Townley Park Stages 62 & 63

Stage 62 drainage has been completed with water service being installed. Stage 63 drainage is underway and is expected to be completed by early December with water installation to follow.
Current Forecast Title Date: May - July 2019

Townley Park Stages 64 & 65

Bulk earthworks has been completed, sewer has commenced in Stage 64 with drainage to follow. Sewer & drainage has commenced in stage 65.
Current Forecast Title Date: May - July 2019

Townley Park Stages 66, 67 & 68

Early works application is currently being reviewed by Wyndham Council with a forecast approval date of early December 2018. Bulk earthworks & sewer to commence December 2018.

Once we have received detailed design approval from Council we will be able to provide a firm date for commencement of main works & subsequent title dates.
Current Forecast Title Date: August – December 2019.

Wetlands next to Larapinta Stage 33

Bulk earthworks of the wetlands reserve situated to the east of Stage 33 has commenced.

Stage 29 Village Park

The park will open to the public early in the New Year whilst we await the arrival of specialist play equipment from Europe and also allow time for the grass to be established.

Construction of the Stage 29 village park is underway and expected to complete November – December 2018.

Ison & Armstrong Roads Update

Armstrong Road & Ison Road intersection and Section 2A all works complete, final authority approval being sought.
Current forecast for completion of Section 2A – December 2018.