Construction Update October 2017


Construction Update October 2017

Welcome to the Aurora construction update. We value our customers and will provide regular updates to keep you up to date on the progress of construction at Aurora.


  • Edgars Road Secondary School works are underway by the Victorian School Building Authority. The building and carpark are both progressing steadily. Image above taken 23 October 2017.

  • Stage 15 – Bulk earthworks are complete, water installation underway. Titles are expected between March 2018 and May 2018.

  • Stage 16 - Bulk earthworks are complete, sewer and drainage underway. Titles are expected between April 2018 and June 2018.

  • Stage 17 – Bulk earthworks are complete, drainage installation underway and sewer to commence shortly. Titles are expected between April 2018 and June 2018.

  • Stage 19 - Bulk earthworks are complete, sewer and drainage installation underway. Titles are expected between June 2018 and August 2018.

  • Stage 20 - Bulk earthworks are complete, sewer and drainage installation underway. Titles are expected between July 2018 and September 2018.

  • Edgars Road electrical reticulation works are underway and asphalt installation is scheduled for the last week of October 2017.