Construction Update July 2017



Welcome to the Aurora construction update.

We value our customers and will provide regular updates to keep you up to date on the progress of construction at Aurora.


  • Stage 8: Works nearing completion with final sections of footpath being installed. Titles expected late July, early August 2017.

  • Stage 11 – Sewer installation is complete, drainage nearing completion and water main under construction. Titles are expected between December 2017 and February 2018.

  • Stage 12 – Sewer installation is complete. Drainage is under construction. Titles are expected between December 2017 and February 2018.

  • Stage 14 – Sewer works nearing completion with drainage to commence shortly. Titles are expected between January 2018 and March 2018.

  • Stage 15 – Bulk earthworks are complete with sewer to commence shortly. Titles are expected between March 2018 and May 2018.

  • Stage 16 - Bulk earthworks are underway. Titles are expected between April 2018 and June 2018.

  • Stage 17 – Bulk earthworks are underway. Titles are expected between April 2018 and June 2018.

  • Stage 19 – Bulk earthworks commencing soon. Titles are expected between June 2018 and August 2018.