Atherstone Construction Update – September 2017

Stone Ridge 8

Civil works are complete and working with local authorities to complete their final audits and approval.



Settlers Creek 1-5

Stages are nearing completion and are forecasted to be delivered two weeks apart in sequential order.

  • Concrete works are finalising progressively
  • Top soil to commence
  • Line-marking is incomplete
  • Authority auditing & sign-off

Settlers Creek 6 & 7

  • Kerb & Channel to commence
  • Electrical and optic fibre cables commencing soon

Settlers Creek 8 & 9

  • Sewer is complete
  • Drainage is finalising
  • Boxing
  • Water reticulation

Settlers Creek 10 & 11

We’re delighted to announce work has commenced on Wilton Fields 6 and Settlers Creek 10 & 11.


  • Bulk earthworks and stripping is complete
  • Sewer trenching has commenced
  • Main drain to follow