Living Here

Development Update


Information provided below is correct as at 02/07/2019.

Atherstone truly is ‘A Place on the Go’ with exciting construction activity happening in all directions! We’re delighted to bring you our latest update, highlighting the progress of civil construction, community infrastructure and amenity announcements.

It is incredible the growth that has occurred in the Atherstone Community over the past 12-months. We have delivered 20 new stages, comprising of 1,000 blocks, all titled and ready for new homes to be constructed and new residents to move in.

Additionally, amongst developing the vast number of blocks, Atherstone's social and physical infrastructure has progressed quickly too. This includes delivery of wetlands, parks, trails, playgrounds, roads, bridges, Access Point Library (pop up library lockers), community and children facilities…and so much more.

We are excited to see you build your home in Atherstone and thrive in the amazing community.

Cobblebank Train Station Update

We were delighted by the recent visit of Premier Dan Andrews to Atherstone’s Cobblebank Station last week. His visit reiterated the ongoing commitment to building the infrastructure that this local community needs to grow. Along with the station opening later this year there will also be a new bus service, route 454, that will use Cobblebank Station's bus interchange.

Additionally, Atherstone's Cobblebank Station are in the midst of a two-week construction blitz concluding Sunday 7 July. Throughout the construction blitz a 400-strong construction crew working around the clock along the Ballarat Line Upgrade. In this period coaches will replace V/Line trains between Ballarat and Melbourne.

We are excited for Cobblebank Station opening late-2019.

Wilton Fields Village Park

The construction of Wilton Fields Village Park, located at the corner of Colosseum Drive and Wimbledon Avenue, is quickly progressing. This week marks the installation of the new DNA climbing tower which stretches as high as 7.2m. At completion, the park will also include plenty of green open space, large shelter with BBQ, swings, super slide and see-saw.

We are excited for the opening in Spring 2019.

Toolern Creek Pedestrian Bridge

Preliminary works, including geotechnical testing, has commenced on the Toolern Creek Pedestrian Bridge. The bridge is located adjacent to Settlers Creek Stage 8, connecting the Atherstone Community to schools and community centres on the west side of Toolern Creek.

The pedestrian bridge is anticipated to open in time for the 2020 school year. This will provide walkable access to Melton South Primary School and St Anthony's Primary School.

Settlers Creek Village Park

The waterplay equipment is currently being installed in Settlers Creek Village Park. This is the final step in completing the park ready for the public. Concurrently, the park's vegetation is establishing well in the new habitat.

Stay tuned for the official opening event for Settlers Creek Village Park in late-July.

Most recently, congratulations to Wilton Fields Stage 12 purchasers on your titled lots.

We would also like to congratulate purchasers from the 20 new stages titled over the last year.

We look forward to seeing your new homes under construction and welcoming you to the Atherstone community.

Middle Park - Stage 18

The final stages of construction for Middle Park Stage 18 are being completed. Final Statement of Compliance audits are in the process of being undertaken to enable registration at the Titles Office.

Settlements are forecast to occur late in August 2019.

Please contact your conveyancer and finance provider to prepare for upcoming settlement. Bank valuation access is now available.

Middle Park

Stages 20
Electrical cable installation is complete. Kerb installation has commenced. Settlements are forecast to occur between August to September 2019.

Stage 21
Electrical cable installation is in progress. Kerb installation has commenced. Settlements are forecast to occur between August to October 2019.

Stage 22
All concrete works, including kerb, concrete footpaths and driveway crossovers are now complete. Settlements are forecast to occur between August to October 2019.

Stage 23
Kerb and channel works are complete and work has begun on concrete footpaths and driveway crossovers. Settlements are forecast to occur between August to October 2019.

Park Edge

Stage 24
Water installation is complete, with road crossings and pavement in progress. Settlements are forecast to occur between November 2019 and January 2020.

Stage 25
Water installation is complete, with road crossings and pavement in progress. Settlements are forecast to occur between January to March 2020.

Stage 26
Earthworks are complete, with water installation is in progress. Settlements are forecast to occur between February and April 2020.

Stage 27
Earthworks and sewer installation are completed. Settlements are forecast to occur between June to November 2020.

Additionally, the next section of Atherstone Boulevard that stretches through Park Edge is under construction.

Palara

Stage 31
Bulk earthworks are complete, with sewer complete underway with drainage in progress. Settlements are forecast to occur between February and April 2020.

Stage 32
Bulk earthworks are nearing completion. Sewer installation is in progress and drainage works have commenced. Settlements are forecast to occur between February and April 2020.

Stage 33
Bulk earthworks are complete, with sewer installation in progress. Settlements are forecast to occur between June and November 2020.

";