Information provided below is correct as at 24 November 2022.

Watch our recent development update video below:

Some of Yarrabilba's recent highlights have been:

  • Second state primary school announced "South Rock State School"- due to open 2023! Learn more here
  • The Rail Trail from Logan Village to Yarrabilba is now open - learn more
  • Our Instagram page is growing too - now over 1,200 followers - join us at @MyYarrabilba


As always, if you'd like to know more about anything included in this update, feel free to contact us on 1800 721 856 or yarrabilbacustomersevice@lendlease.com

 

The Parks and Mallee Pocket

Construction across The Parks, Mallee Pocket and associated road infrastructure continued this month with some delays due to inclement weather.

Refer to the village plans to confirm your stage number. If site access is available for your stage, please contact Tracie, Jenna or Ryan on 1800 721 856 or yarrabilbacustomerservice@lendlease.com to book a time to access the site with Goldings.

The Parks Village Plan

Mallee Pocket Village Plan

The Parks Stages 2, 3, 5 & 6 Image

The Parks Stages 2, 3, 5 & 6

Construction updates:

  • Stage 2 and 5 are complete and now open with unrestricted access.
  • Stages 3 and 6 has seen continued retaining and fencing installation, with landscape works due to commence shortly.

 

Valuation access, soil testing and registration anticipated time frames:

  • Stage 3 & 6 valuation access - is available now
  • Stage 3 soil testing - is proposed to be available from late November 2022
  • Stage 6 soil testing - is proposed to be available from mid December 2022
  • Stage 3 - has now registered
  • Stage 6 - has now registered

 

Site access to be confirmed on an individual basis, subject to the information required from the surveyor/valuer. Photos can be provided to assist to establish if the site is ready for their purposes.

The Parks Stages 4 & 8 Image

The Parks Stages 4 & 8

Construction updates:

  • Stages 4 has seen the continued construction of retaining walls and construction of stormwater. Mulching works have commenced on the batters in Stages 4 and 8.

 

Valuation access, soil testing and registration anticipated time frames:

  • Stage 4 valuation access - is available now
  • Stage 4 soil testing - is proposed to be available from mid December 2022
  • Stage 4 registration - anticipated December 2022 (weather permitting)
  • Stage 8 valuation access - is proposed to be available from mid January 2022
  • Stage 8 soil testing - is proposed to be available from late January 2022
  • Stage 8 registration - anticipated January 2023 (weather permitting)

 

Site access to be confirmed on an individual basis, subject to the information required from the surveyor/valuer. Photos can be provided to assist to establish if the site is ready for their purposes.

Stages 7-12 pictured

The Parks Stages 7 & 9 Image

The Parks Stages 7 & 9

Construction updates:

The construction of retaining walls has continued in Stage 7. The planning of stormwater and sewer works for both Stages 7 & 9 has commenced.

Valuation access, soil testing and registration anticipated time frames:

  • Stage 7 & 9 valuation access - is proposed to be available from mid January 2023
  • Stage 7 & 9 soil testing - is proposed to be available from late January 2023
  • Stage 7 & 9 registration - anticipated March 2023 (weather permitting)

 

Site access to be confirmed on an individual basis, subject to the information required from the surveyor/valuer. Photos can be provided to assist to establish if the site is ready for their purposes.

Stages 5, 6 and 7 pictured

The Parks Stages 10, 11, 12 & 24 Image

The Parks Stages 10, 11, 12 & 24

Construction updates:

  • Stages 10, 11, 12 and 24 have commenced with the construction of retaining walls and the planning for stormwater and sewer construction.

 

Valuation access, soil testing and registration anticipated time frames:

  • Stage 10, 11 & 12 valuation access - is proposed to be available from mid February 2023
  • Stage 10, 11 & 12 soil testing - is proposed to be available from late February 2023
  • Stage 10, 11 & 12 registration - anticipated March 2023 (weather permitting)
  • Stage 24 valuation access - is proposed to be available from March 2023
  • Stage 24 soil testing - is proposed to be available from late March 2023
  • Stage 24 registration - anticipated April 2023 (weather permitting)

 

Site access to be confirmed on an individual basis, subject to the information required from the surveyor/valuer. Photos can be provided to assist to establish if the site is ready for their purposes.

Stages 7-12 pictured

Mallee Pocket Stages 19 to 22 & 27 to 29 Image

Mallee Pocket Stages 19 to 22 & 27 to 29

Construction update:

  • Mallee Pocket has seen earthworks continue over the precinct and the commencement of planning works for sewer construction.

 

Valuation access, soil testing and registration anticipated timeframes:

  • All stages - valuation and soil testing  access dates are not yet confirmed
  • All stages - anticipated registration July 2023 (weather permitting)

Non-residential development

The $7.4m new community hub has a name! Image

The $7.4m new community hub has a name!

The naming off the hub was put to the local community through a Council survey, who chose the name, the Buzz.

The hub will be an inclusive, engaging, and responsive place that enables a thriving community to connect, learn, earn and innovate. The facility will create 22 construction jobs, support supply chains and play an important role in our region’s economic recovery.

New Neighbourhood Shopping Centre now open Image

New Neighbourhood Shopping Centre now open

The brand new neighbourhood centre is now open and home to a bakery, newsagency and hair salon along with a second Harmony Early Learning Centre, Anytime Fitness, Cafe 63 and other retailers opening soon!

Specialist Health Centre underway Image

Specialist Health Centre underway

Located on Adler Circuit, 'Yarrabilba Health City’ will incorporate speciality units for Cardiology, Oncology, radiology, a dental surgery, and allied health care. Base building construction is complete with fitouts underway.

Yarrabilba Tavern Image

Yarrabilba Tavern

Work on the tavern site is progressing well with opening expected mid 2023!

The venue will offer new dining areas, kid's zones, a sports bar and a stunning outdoor area.