The exciting vision for Figtree Hill is fast becoming a reality! Works are progressing well on-site and we are excited to share with you the latest progress update as the community continues to take shape.
If you have any questions, please contact us on 1300 144 532, or visit us at the Figtree Hill Sales & Information Centre.
- Close all
-
Project Update
Key Progress:
- Installation of light poles is now complete in Stages 1A & 1B
- Streetscape works in Stages 1A & 1B have commenced
- Approval to commence construction works to Stages 1C, 1D & 1E has been received – our civil contractor will commence works this month
- Future Adventure Playground has received development approval by Campbelltown City Council
Next Steps:
- Continue the installation of external servicing infrastructure
- Continue streetscape works, including the planting of more than 900 street trees and more than 9,000 plants
Information provided below is correct as at 10 October 2023 and is provided as a general guide only.
- Close all
-
Appin Road Upgrade Works
Transport for NSW has officially approved Lendlease’s plan to upgrade Appin Road!
The $170 million package of works will improve the safety and quality of this vital piece of road infrastructure, a key arterial connecting south-western Sydney with the Illawarra.
For homebuyers and future residents, the road upgrade will facilitate the start of construction of more than 450 homes and, once complete, will provide an easier and safer commute for families. It will also deliver improvements to help protect local koalas, including fencing and underpasses.
What this means for residents?
- The construction of an intersection providing you with safe access into Figtree Hill can now commence – works are set to start this year.
- Once construction commences, we will provide you with a more accurate update on the registration timings of your lot at Figtree Hill.
For further information on the upgrades, click here.