Living Here

Development Updates

 

Information provided below is correct as at 24th July 2018.

Development to Date

July has been a busy month at Harpley with construction progressing well. Major construction works are underway on the Armstrong Road & Ison Road intersection with road box-out commenced. The team is also making good progress on the wetlands rectification in Carinya Precinct, also the wetlands that lie north of Shearwater Place.

In terms of stage construction, we expect to achieve titles on Stage 54 in early August. Shearwater Place Stages 52 & 53 and Townley Park Stage 61 are also progressing well with titles expected between October and December this year. Townley Park Stages 62 & 63 should follow shortly after, with titles expected between December 2018 and February 2019.

View our Project Overview video to see construction progress at Harpley.

Larapinta Stage 33

Sewer & drainage complete, water reticulation commenced, road box out to commence late July.

Current Forecast Title Date: December 2018 – Feb 2019.

Shearwater Place Stage 54

Construction works have been completed, currently working with authorities to achieve Statement of Compliance.

Current Forecast Title Date: August.

Shearwater Place Stages 52 & 53

Bulk earthworks and sewer works have been completed, drainage currently under construction.

Current Forecast Title Date: October – December 2018.

Townley Park Stage 61

Drainage and water reticulation completed with road box out to commence late July.

Current Forecast Title Date: October – December 2018.

Townley Park Stages 62 & 63

Bulk earthworks are completed, sewer works commenced.

Current Forecast Titles: December 2018 - February 2019.

Drainage Reserve 6 (north of Stages 52 & 53)

Drainage Reserve 6 located to the north of Stages 52 & 53 has commenced, with completion scheduled for early August.

Armstrong Road Update

Armstrong Road & Ison Road intersection and section 2A drainage works are complete and road box out has commenced.

The construction of the culvert on Armstrong Road is also complete.

Current Forecast for completion of Section 2A: December 2018.