Information provided below is correct as at 6 September 2018.

With continued construction and upcoming infrastructure and community additions, the Atherstone site is a hive of activity. We thank you for your patience as we construct your new blocks.

Please take this opportunity to update your conveyancer, bank, and builder with current settlement forecast dates.

Development to Date

Atherstone continues to develop and grow into a fantastic community. There’s a hive of activity across the project, with all the stages in the Settlers Creek, Wilton Fields, and Middle Park neighbourhoods under construction. Watch the latest drone footage to get a bird’s eye view of all the fantastic existing amenity including Atherstone’s Western BACE, the regional play space, regional sports precinct, wetland, and the network of hike and bike trails as well as the location of exciting new amenity including the new Toolern train station under construction, childcare centre, and future proposed neighbourhood activity centre, sports ovals and major town centre

Diamond Parade Roundabout

The intersection at Diamond Parade and Bridge Road is being upgraded to a brand-new roundabout. We are nearing the final stages of works and authority’s compliance at this intersection. We look forward to announcing a reopening date. Visit our Facebook page or latest updates.

Settlers Creek – Stage 7

This stage has now passed all audits and is currently in the process of obtaining Statement of Compliance certification from the authorities. Construction is complete. This stage is available for valuation inspections. Settlements are currently forecast to occur in October 2018.
A team member will be in touch once compliance has been achieved. If you haven’t already done so, please contact the Sales Office with your conveyancer’s details and have your finance organised in preparation for settlement.

Settlers Creek - Stage 8

This stage has now passed all audits and is currently in the process of obtaining Statement of Compliance certification from the authorities. Construction is complete. The stage is available for valuation inspections. Settlements are currently forecast to occur in October 2018. A team member will be in touch once compliance has been achieved.

Settlers Creek – Stage 9

This stage has now passed all audits and is currently in the process of obtaining Statement of Compliance certification from the authorities. Construction is complete. The stage is now available for valuation inspections. Settlements are currently forecast to occur in late October to November 2018. A team member will be in touch once compliance has been achieved.

Settlers Creek - Stage 10

Construction is now complete. This stage has achieved Practical Completion, and is currently in the process of scheduling audits to obtain Statement of Compliance certification from the authorities. Settlements are currently forecast to occur in November 2018.

Settlers Creek – Stage 11

Footpath and topsoil works have been completed, with asphalt works to follow. Settlements are currently forecast to occur between October – December 2018.

Settlers Creek – Stages 12 & 13

Construction works are progressing well. Earthworks are nearing completion and sewer and drainage works are in progress. Settlements are currently forecast to occur between May and June 2019.

Wilton Fields - Stage 6

This stage is at the auditing stage of obtaining Statement of Compliance certification from the authorities. Construction is complete. Settlements are currently forecast to occur in November 2018. This stage is available for valuation inspections. We are working with the contractors and authorities to ensure delivery of this stage at the earliest possible and an Atherstone team member will be in contact with purchasers for further updates.

Wilton Fields - Stage 7

Footpath and topsoil works have been completed, with final asphalting works to follow. Settlements are forecast to occur between November and December 2018.

Wilton Fields - Stage 8

Kerb and channel works have now been completed, with footpath and asphalting to follow. Settlements are forecast between November and January 2019.

Wilton Fields - Stages 9

Kerb and channel works have now been completed, with footpath and asphalting to follow. Settlements are forecast between December and February 2019.

Wilton Fields - Stage 10, 11 & 12

Water mains installation and road boxing works are in progress, with road pavement works to follow. Settlements are forecast for:

  • Wilton Fields Stage 10 – between March and May 2019
  • Wilton Fields Stages 11 & 12 – between April and June 2019.

Middle Park - Stages 13 - 23

All Middle Park Stages have commenced construction, and are currently in the bulk earthworks stage, with sewer and drainage works also in progress. Settlement forecasts:

  • Middle Park stage 13, 14, 15 – between April and June 2019
  • Middle Park stage 16, 17, 18, 19 – between May and July 2019
  • Middle Park stage 20, 21, 22 – between June and August 2019
  • Middle Park stage 23 – between August and October 2019

Ballarat Line Upgrade

Construction works on the Ballarat Line Upgrade are progressing well. Recent site clearance works east of Ferris Road herald the start of construction at the new Toolern Train station. Construction of a second track between Melton and Caroline Springs and a new rail bridge over Toolern Creek, have been underway for some time.

Bridge Road Bridge

Bridge deck and retaining wall works have now been completed, with asphalt works to follow. Watch the video to see recent construction progress and we look forward to providing further updates as we approach our anticipated Spring 2018 opening.

Build Melton Hospital

The City of Melton recently launched a campaign calling on all parties contesting the 2018 Victorian Election to commit to building a public hospital in the City of Melton. The hospital would be located in Atherstone, close to the future Toolern Train Station.
Melton Hospital is proposed to be a 24-hour public hospital with a full range of services such as an emergency department, cardiac and intensive care, acute surgical facilities and diagnostic services.