Information provided below is correct as at 1st May 2018.


The Atherstone site is a hive of activity with construction now progressing at a strong pace and we look forward to welcoming you to your new home. We thank you for your patience as we construct your new lots.

Please take this opportunity to update your conveyancer, bank, and builder for current settlement forecast dates.

Stone Ridge – Stage 9

Construction is forecast for completion in May. Final compliance audits are currently taking place with Settlements currently forecast to occur between June and July 2018.

Settlers Creek – Stages 4 & 5

Construction works are now complete. We are currently in the process of obtaining electrical works Statement of Compliance. Settlements are currently forecast to occur in June 2018.

Settlers Creek – Stages 6 & 7

Construction works are now complete. We are currently in the process of obtaining works Statement of Compliance. Settlements are currently forecast to occur between June and July 2018.

Settlers Creek – Stage 8

Asphalting works are nearing completion, with final sections remaining. Topsoil and line marking works will follow in May. Settlements are forecast to occur between June and August 2018.

Settlers Creek – Stage 9

Asphalting works are nearing completion, with final sections remaining. Topsoil and line marking works will follow. Settlements are forecast to occur between July and September 2018.

Settlers Creek – Stage 10

Installation of electrical and communication services are nearing completion. Road works are to follow. Settlements are forecast to occur between August to October 2018.

Settlers Creek – Stage 11

Drainage works are nearing completion. Road work construction has commenced, with electrical trenching also underway. Settlements are forecast to occur between September to November 2018.

Settlers Creek – Stage 12

Melton Council have completed phase 1 remediation works. Phase 2 have now commenced and are expected to progress through to June. Settlements are forecast to occur between March – May 2019.



Settlers Creek – Stage 13

Bulk earthworks are expected to re-commence in July 2018. Settlements are forecast to occur between March – May 2019.

Wilton Fields – Stage 6

Civil construction has finished and the contractor is testing the services and seeking approval from each authority. Street trees are also set to be installed. Settlements forecast to occur between June to July 2018.

Wilton Fields – Stage 7

Drainage works are complete, with sewer not far behind. All roads have been cut and the contractor has commenced placing the road base. Water mains have commenced. Settlements are forecast between October to December 2018.

Wilton Fields - Stage 8

Drainage, Sewer and the road boxing is nearly complete. Settlements are forecast between October to December 2018.

Wilton Fields - Stage 9

Drainage and Sewer works are making good progress and road boxing has started. Settlements are forecast be November to January 2019.

Wilton Fields – Stages 10, 11, & 12

The contractor has started on site, installing site boundary fencing, stripping the topsoil and grass to commence the earthworks. Settlements are forecast for:

  • Wilton Fields Stage 10 – between January to March 2019
  • Wilton Fields Stage 11 – between February to April 2019
  • Wilton Fields Stage 12 – between March to May 2019


Middle Park - Stages 13 to 19

Middle Park Stages 13 to 19 works are expected to be awarded in June 2018 for onsite commencement thereafter.

";