Harpley Construction Update – September 2017


Harpley has a number of stages under construction that are due to title before Christmas. Unfortunately some delay in title timing has been encountered for Stages 25, 26, 28 & 29, due to a delay in authority approvals. Stage 31 Larapinta is progressing well and roads are starting to take shape. Carinya Village Park is well underway with expected completion in November 2017.

Stage 25

All main construction works complete, final authority approval being sought.

Current Forecast Title Date: Mid-December 2017.

Stage 26

All main construction works complete, final authority approval being sought.

Current Forecast Title Date: Mid-December 2017.

Stage 28

Majority of main construction works complete, road asphalt works underway, line marking & street signs scheduled for late September.

Current Forecast Title Date: Late November – Mid December.

Stage 29

Majority of main construction works complete, road asphalt works underway, line marking & street signs scheduled for late September.

Current Forecast Title Date: Late November – Mid December.

Stage 31

Road box out complete, servicing underway and kerb and channel to commence shortly.

Current Forecast Title Date: Late February 2018.

Wetlands

Stage 28/29 wetland excavation progressing well.

Armstrong Road

Stage 1 Armstrong Road culvert installation complete, backfill underway. Drainage has commenced.

Carinya Village Park

Footpaths and shelter structure complete, decking overlooking playground underway. Topsoiling for lawn and planting being prepared with play and park equipment installation to commence shortly. Click here to view a detailed plan of what the park will look like (artists impression only).


Due for completion: November 2017