Harpley Construction Update – August 2017


Harpley has been a hive of construction activity over recent months with the fairly dry weather allowing us to make good progress with construction of Shearwater stages 24 - 29, the adjoining wetlands, parts of Armstrong Road and Larapinta 31.  Carinya Village Park is also well underway with expected completion in November.

Stage 24

Status: All main construction works complete, final authority approval being sought

Current Forecast Title Date: 31/08/2017

Stage 25

Status: Majority of main construction works complete, road asphalt works underway, line marking & street signs schedule for mid-August.

Current Forecast Title Date: 29/09/2017

Stage 26

Status: Majority of main construction works complete, road asphalt works underway, line marking & street signs schedule for mid-August.

Current Forecast Title Date: 09/10/2017

Stage 28

Status: Services & road boxing complete, road subgrade currently being placed.

Current Forecast Title Date: 19/10/2017

Stage 29

Status: Services & road boxing complete, road subgrade currently being placed.

Current Forecast Title Date: 13/11/2017

Stage 31

Status: Sewer & bulk earth works complete, road box out currently occurring, services to follow.

Current Forecast Title Date: 29/01/2018

Wetlands east of Shearwater

Drainage reserve complete, wetlands progressing well, started at northern section moving south.

Armstrong Road

Sewer works complete Culvert currently being excavated, drainage due to start Mid-August.

Carinya Village Park

Status: Site grading and levels complete, footpaths also largely complete. Shelter structure has been erected. Click here to view a detailed plan of what the park will look like (artists impression only).

Due for completion: November 2017