Harpley Construction Update – June 2017

 

 

Melbourne has been blessed with a fairly dry start to winter and as such we are on track to deliver Shearwater stages 24 – 29.  There are some minor delays to Stages 25 and 26 that have resulted due to coordination issues with the water authority branch sewer, but these issues are now resolved and work is progressing well. Construction work in Stage 31 Larapinta will commence before the end of this month.

Shearwater Stage 24

All main construction works complete, line marking will be occurring over the next week. Authority approvals being sought.

Current Forecast Title Date: 31/07/2017

Shearwater Stage 25

Main services works are complete with the exemption of electrical services. Asphalt and kerb has been complete.

Sewer works & electrical service to be completed over the next 4-6 weeks.

Current Forecast Title Date: 22/09/2017

# Stages 25 & 26 has been delayed slightly due to coordination issues with the water authorities branch sewer.

Shearwater Stage 26

Main services works are complete with the exemption of electrical services. Asphalt and kerb has been complete.

Sewer works & electrical service to be completed over the next 4-6 weeks.

Current Forecast Title Date: 10/10/2017

# Stages 25 & 26 has been delayed slightly due to coordination issues with the water authorities branch sewer.

Shearwater Stage 28

Sewer works complete, Road box out complete, road sub base to be placed over the next 4 weeks.

Current Forecast Title Date: 02/11/2017

Shearwater Stage 29

Sewer works complete, Road box out complete, road sub base to be placed over the next 4 weeks.

Current Forecast Title Date: 20/11/2017

Larapinta Stage 31

Sewer works complete, main civil construction works scheduled to commence end of June. Authority approval required prior to commencement.

Current Forecast Title Date: 08/02/2018