Aurora Construction Update February 2018

 

We value our customers and will provide regular updates to keep you up to date on the progress of construction at Aurora.

 

Stage 11 & 12

Stage 11: Titles have registered and settlements commenced.

Stage 12 - All services have been installed, pavement complete and the authority approval process is underway. Titles are expected in February 2018.

Stage 14, 15 & 16

Stage 14 - All services have been installed, pavement complete and concrete works are underway. Titles are expected between March and April 2018.

Stage 15 – Road pavement and electrical installation underway. Titles are expected between March 2018 and May 2018.

Stage 16 – Water, sewer and drainage complete with pavement construction underway. Titles are expected between April 2018 and June 2018.

Stage 17

Stage 17 – Sewer and drainage are complete with water installation nearing completion. Titles are expected between May 2018 and July 2018.

Stage 19 & 20

Stage 19 – Sewer and drainage works complete with water installation nearing completion and pavement construction underway. Titles are expected between June 2018 and August 2018.

Stage 20 - Bulk earthworks are complete with sewer and drainage installation nearing completion. Watermain installation is underway. Titles are expected between July 2018 and September 2018.

Edgars Creek Secondary College

Edgars Creek Secondary College construction is well underway by the Education Department. The college commenced year 7 curriculum from Mernda College this week. The college is set to open its doors from Term 3 2018. Download the Aurora Education Brochure for a full list of early learning, primary, secondary, and tertiary education facilities in the area.

Edgars Road

Edgars Road construction is complete and the authority compliance approval process is underway with the road expected to be open in late February, early March 2018.

";