Atherstone Construction Update - November 2017

 

Atherstone Project Update November 2017

 

Stone Ridge 8

Construction works complete. Lendlease has recently received approval from the final service authority and are expected to lodge for titles in December 2017. 

It is likely that purchasers in this stage will have an opportunity to settle prior to January 2018.

 

Stone Ridge 9

Forecast construction works to commence in December 2017 include kerb and channelling, formation of electrical and communication trenches and acoustic treatments on the northern boundary.

Settlements targeted in April – June 2018.

Watch the Construction Update

Settlers Creek Stages 2 & 3

Settlers Creek 1

Construction works complete. Lendlease has recently received approval from the final service authority and are expected to lodge for titles in December 2017.

It is likely that purchasers will have an opportunity to settle prior to January 2018.


Settlers Creek 2 & 3

Construction works complete. Lendlease is in the process of obtaining final authority approvals to enable settlements in January – February 2018.

Settlers Creek 4 & 5

Construction works near complete with top soil and lining marking forecast to commence in December 2017. Lendlease is in the process of obtaining authority approvals for settlements in January – March 2018.

Settlers Creek 6 & 7

Forecast construction works to commence December 2017 include lot grading, top soiling and base course asphalt works.

Settlements targeted in March – May 2018.

Settlers Creek 8 & 9

Forecast construction works in December 2017 include kerb and channelling, formation of electrical and communication trenches and commencement of base course asphalt works.

Settlements targeted in April – June 2018.

Settlers Creek 10

Bulk earthworks and sewer trenching complete. Forecast construction works to commence in December 2017 include drainage trenching.

Settlements targeted in June – August 2018.


Settlers Creek 11

Bulk earthworks complete. Forecast construction works to commence in December 2017 include sewer and drainage trenching.

Settlements targeted in August – October 2018.

Settlers Creek 12 & 13

Contractor awarded with bulk earthwork commencing in 2018.

Settlements targeted in October – December 2018.

Wilton Fields 6

Installation of sewer and drainage near complete. Forecast works to commence in December 2017 include road subgrade.

Settlements targeted in April – June 2018.

";